Return to Warm Shell + Partial Fitout
Kings Row, Milton
PROJECT SUMMARY:
Strip out of existing office space on Level 4 + Level 6 and return to warm shell for re-leasing purposes. Construction of new staff kitchen and modification to existing meeting rooms to entice new tenants.
PROJECT DETAILS:
Timeline: 8 weeks construction
Project GFA: 1430m2
Location: Kings Row, Milton
PROJECT FEATURES:
Working in a live environment meant managing materials in and out around busy lift periods (arrival, lunch, departure).
Working adjacent to a highly sensitive radio station recording studio. Noisy works and works causing any vibration needed to be completed whilst the radio station was off-air, so as not to impact their recording equipment.
Programming of works across two levels to occur as a flow on, stripping out Level 4 initially, then flowing to Level 6, with the rest of the trades following suit.
Working within the parameters of the existing plumbing when constructing the new kitchenette that was more modern in form and size.